Taman Warisan landslide: Phase two piling work 50% complete – Police

KUALA LUMPUR: Phase two of the sheet piling work in the drain area near the landslide location at Jalan Wawasan 3/9 Taman Wawasan is now 50 per cent complete.

Serdang district police chief ACP A Anbalagan said that 590 sheet piles, including 375 in the phase one area, have been installed to help stop any soil movement.

“The estimated time of completion by the contractor is two weeks, depending on current weather conditions,” he told Bernama today.

Even though it has been raining frequently in the past few days, there has been no soil movement reported in the area.

The landslide that occurred on Dec 16 forced 29 residents from nine terrace houses in Taman Wawasan Puchong to evacuate due to safety concerns.–Bernama

STAY AHEAD OF THE CURVE

Join our community for instant updates and exclusive content.

Join Telegram Channel

Related


spot_img

Latest News

Bora Pharmaceuticals Completes Acquisition of MacroGenics’ Rockville Manufacturing Operations

TAIPEI, TAIWAN - Media OutReach Newswire - 2 July 2026 - Bora Pharmaceuticals Co., Ltd. ("Bora" or "Bora Group"; TWSE: 6472; OTCQX: BORAY) today announced the completion of its acquisition of the GMP manufacturing operations of MacroGenics, Inc. (NASDAQ: MGNX) including its biologics drug substance facility in Rockville, Maryland and an associated warehousing center in Frederick, Maryland, for total consideration of US $122.5 million through its wholly owned subsidiary Bora Biologics USA, LLC.. Upon closing, Bora signed a long-term CDMO Service Agreement with MacroGenics.

Most Viewed

spot_img
WC26

World Cup 2026

Updates, Fixtures, Results & Standings