SMG flood mitigation initiative increases Klang River capacity by 18% – LLSB

State Election

Johor State Election 2026

11 July 2026 Johor, Malaysia
Learn more

SHAH ALAM: A major flood mitigation initiative under the Selangor Maritime Gateway (SMG) project has successfully increased the Klang River’s water capacity by 18 per cent, covering a 31-kilometre stretch from the river mouth to the Petaling Jaya-Kuala Lumpur border.

Syaiful Azmen Nordin, managing director of Landasan Lumayan Sdn Bhd (LLSB), a wholly-owned subsidiary of Menteri Besar Selangor (Incorporated) appointed as the master developer of the SMG project, said the improved river section spans two of four key project blocks – from the Shah Alam-Klang border to the Shah Alam-Puchong border, and from the river mouth to Bandar Klang – identified as Blocks 3 and 1, respectively.

He said that the state government, through its agencies, is targeting a total increase of at least 40 per cent in river capacity by the end of this year after past data revealed that Klang River, especially in Selangor, could not accommodate upstream water overflow during heavy rains.

“Block 3, which covers flood-prone areas such as Sri Muda, Kota Kemuning, Section 17, and Section 24, requires special attention, as these are the most affected zones in recent flood events,” he told reporters after a site visit to the flood mitigation project in Kota Kemuning today.

The river widening and dredging works for the remaining two blocks – from Bandar Klang to Bandar Sultan Sulaiman (Block 2), and from the Shah Alam-Puchong border to Petaling Jaya-Kuala Lumpur (Block 4) – will begin next year, covering an additional 28.8 km.

According to Syaiful Azmen, construction on Blocks 1 and 3 is expected to be completed by year-end, after which a two-year enhancement and monitoring phase will begin, also managed by LLSB.

To date, around 94,000 tonnes of waste have been extracted from the river, at an estimated handling cost of RM20 million, he said.

“That RM20 million could’ve been used for other development initiatives, if only there was greater public awareness about river cleanliness,” he added.

STAY AHEAD OF THE CURVE

Join our community for instant updates and exclusive content.

Join Telegram Channel

Related


spot_img

Latest News

Booster Pack 09 “Here He Comes! Our Hero!” & Starter Deck 04 “Ultraman &...

Tsuburaya Productions will release Booster Pack 09 and Starter Deck 04 for the Ultraman Card Game on October 23, 2026. The milestone launch introduces the original Showa Ultraman, Ultraman Cosmos, the new Color System and Boost Cards to celebrate the game's second anniversary.

Most Viewed

spot_img
WC26

World Cup 2026

Updates, Fixtures, Results & Standings